Construction progress Alcalá 70

Construction at Alcalá 70 is progressing well.

Structure, foundations and excavation are 100% complete.

Façade finishes are nearly done, with waterproofing at 98% and tiling render at 90%.

Interior plastering is almost complete, and windows are currently in production.

Key installations (plumbing, AC and electrical) are 70% finished.

Kitchens and bathrooms are set to be installed soon.

Interior design elements are in fabrication and the lower garden wall is already in place. Furniture installation will begin soon.